Interior work proceeds in the East Crescent Complex. Some of the apartments will be used as dorm rooms for workshop participants, starting in February 2006. The light-scoop apartment in Unit 6 is almost complete.
[Photo & text: sa]



?

All stages of interior work on this apartment have been experienced by the last workshops. Utilitiy lines were installed, which include hydronic floor heating. Walls were framed ....
[Photo & text: sa]



?

.... and insulated with natural cotton material. More on insulation installation to be posted on 9/12.
[Photo & text: sa]



?

Drywall is installed, taped and mud applied before painting.
[Photo: Noh Hyun-Suk & text: sa]