? The bathroom of Unit 7 is almost complete.

? Faucets, shower heads and handles are installed.

? The concrete sink counter was poured by Planning coordinator Dan Kelliher. Concrete was mixed with very fine gravel and sand and blue pigment was added to the wet mixture. The concrete was carefully screed to achieve a very smooth surface.