This continues the report from 6/27/07, on construction at the new Visitors Center entrance. The crew leveled the ground and installed formwork for a new concrete slab, right next to the existing entrance path.
[Photo & text: sa]
This slab will provide parking spaces for handicapped visitors.
[Photo & text: sa]
Smaller slabs are formed up and poured to connect the area to the ramp [see report from 4/30/07]. This report continues on 7/06/07.
[Photo & text: sa]
TrackBacks[0]
Comments[0]
Posted by sue on July 2, 2007 5:34:43 PM MST