? This continues the report from 6/27/07, on construction at the new Visitors Center entrance.
The crew leveled the ground and installed formwork for a new concrete slab, right next to the existing entrance path.


? This slab will provide parking spaces for handicapped visitors.

? Smaller slabs are formed up and poured to connect the area to the ramp [see report from 4/30/07].
This report continues on 7/06/07.