This continues the report from 7/02/07 of construction at the new Visitors Center entrance. Work continues on the wall between the first and second level of the ramp.
[Photo & text: sa]
The wall is formed up in sections. The crew works on one section at a time and gives it time to cure before proceeding to the next.
[Photo & text: sa]
For this wall the concrete is mixed very dense to allow for packing at an angle. This report continues on 7/11/07 with silt construction of a bench right next to the passenger bridge.
[Photo & text: sa]
TrackBacks[0]
Comments[0]
Posted by sue on July 6, 2007 11:03:48 AM MST