Interior construction proceeds on a first floor apartment of Unit 10 in the East Crescent. To continue the report from 9/10/07, we start with a plan of the apartment.
The main room is located in the Unit 10 light scoop with windows facing east and south. Note the curved wall right next to a recessed back entrance/exit.
The main door can be entered from a, yet to be tiled, porch area. Upon entering an open kitchen area is on your right and a bathroom with shower right next to the kitchen.
[Photo & text: sa]
The back door leads to a staircase on the east side of the S.O.D. office unit.
[Photo & text: sa]
Construction crew Melissa Soluski installs insulation material prior to dry wall.
This report continues on 10/3/07 with drywall installation.
[Photo & text: sa]