? We continue our report from 10/24/07, on construction of the new Visitors Center entrance.
The Metal Shop crew installed part of a railing on the second level of the new ramp.
From this view, a new set of stairs is at the far end of the photo.

? We reported on the construction of the stairs on 10/5 and 10/8/07.
New railing is installed on both sides of the stairs and a connection to the ramp railing is in process.

? Metal shop volunteer Darina Trendafilova welds the connecting steel pieces into place.
We continue the report on railing installation on 11/7/07.