Today@Arcosanti

nav nav nav nav nav nav nav nav nav
? We continue our series of reports about the installation of solar panels for lighting the visitors parking lot and the visitors path from the parking lot to the visitors center.
[See prior reports from 2/18 through 3/3, 3/10 and 3/12/08].
The workshop digs a trench for the utility lines along the visitors path.

? Construction crew David Ledbetter installs wiring to lighting fixtures along the path from the visitors parking lot to the Crafts III Visitors Center.

? Breaker boxes are installed at a distribution point close to the visitors parking-lot and behind the Crafts III building [Brendan Scott and David Ledbetter].
Final report on the AOT grant activities will be posted on 3/19/08.