The third day of intensive concrete pours started with work on level 3 of the new ramp for handicapped visitors. Once again a crew of four people with wheelbarrows brought a steady supply of concrete to the ramp crew.
[Photo & text: sa]
Concrete was spread evenly over a steel mesh for reinforcement.
[Photo & text: sa]
A 2by4 is used to completely level the surface even with the top of the form and part of the crew worked on fine finishing of the concrete surface. Report continues on 9/10/08.
[Photo & text: sa]
Posted by sue on September 8, 2008 11:44:40 AM MST