? We continue with a report on the tile work in the small studio apartment, EC Unit 10-1.
Alumnus Dan Kelliher helped with tiling apartments in the East Crescent.
First, whole tiles are laid out, so that the spaces that will require cut tiles can be carefully adjusted.

? The second stage consists of setting the full tiles. Before a tile is set in, a thin layer of thin-set is applied, acting as the adhesive between the tile and the concrete floor.

? In the left side image, mortar has been applied in the grooves between tiles.
In the photo on the right-side, the corner pieces have been cut and laid out.
We will continue with a report on the tiling of the shower in this apartment on 2/2/09.