? To continue the report from 8/19:
Here we see the first pour, distribution and leveling of the concrete onto the framework for the floor slab.

? The staff and volunteers had to work fast to flatten and smoothen out the liquid material before it hardened.

? The other half of the slab was poured early next morning.
Report continues on 8/24/09.